Assess the physical design of the system to determine whether it is ready to be
tested. Do the following:
• Verify there is physical segregation of any mains supply circuits from the
24 Vdc controller circuits.
• Review the arrangements of terminals and the provision of cable entries
for field wiring.Assess the build state of the system against the test documentation. Do the 490NRP25400
following:
• Compare the arrangement of the system with the General Arrangement
drawings to make sure the system has been manufactured and
assembled correctly.
• Verify that every item shown in the bill of materials on the General
Arrangement drawings is either in place or is available to be installed.
• Check that any special features, configurations or options called for on
the drawings are present and correct.
• Check nameplates and identification labels against the drawings.
Identify any non-conformance found between the system and the drawings. If
appropriate, correct the drawing. Record each non-conformance in the log
book.Carry out a mechanical inspection to verify that an acceptable standard of 490NRP25400
workmanship has been achieved in the assembly and wiring and that the test
arrangements are correct. Do the following:
• Visually inspect the controller and verify that base units, modules and
terminals are free of damage.
• Review the termination of system cabling against the drawingThe power distribution and first power up verifies that the power distribution
circuits function as designed and as detailed in the drawings. It shows the
correct voltages are appearing, and only in the correct places. It also provides
an opportunity to verify correct operation of any power indicators outside the
controller itself. 490NRP25400
Do the following:
1. Make sure all modules are removed.
2. Trip all circuit breakers and disengage all power distribution fuses and
field fuses.
3. Apply power to the incoming power terminals.
4. It is good practice to switch on power supplies to field devices before
supplies to the controller. Devise a formal sequence in which to switch on
individual circuits. 490NRP25400
• In sequence, check each circuit breaker or fuse for zero volts on the
destination side, and then close the circuit breaker or fuse and verify that
the appropriate voltage appears.
• Check that any associated power indicator is lit.
• As each circuit breaker is tested, leave the breaker in the ‘on’ position so
that any unwanted connection between different power circuits can be
detected.
Product picture display
bout us service idea
The company takes production suspension control system parts and components as its dominant products
As long as it is what you want, I can help you find it! Good price! Our purpose:
Build customer relationship with sincerity
Obtain customer satisfaction through service
Win the trust of customers with products
Improve work efficiency with actions
Please contact us for the products you need urgently!
You can’t find the product. Please contact us!
Products you can’t buy. Please contact us!
Email: onewwww@foxmail.com
Introduction to main products
Focus on DCS, PLC, robot control system and large servo system.
Main products: various modules/cards, controllers, touch screens, servo drives.
Advantages: supply imported original products, professional discontinued parts, fast delivery, accurate delivery time,
Main brands include ABB Bailey, GE/FANC, FOXBORO, Invensys TRICONEX, Bentley BENTLY, A-B Rockwell, Emerson EMERSON, OVATION, MOTOROLA, XYVOM, Honeywell HONEYWELL, Rexroth, KUKA, NI, DEIF, Yokogawa, Woodward WOODWARD, Ryan, Schneider SCHNEIDER, Yaskawa, Moog MOOG, PROSOFT and other brands
reminder
For more products, please contact the email for inquiry onewwww@foxmail.com
This article from the temporal Ming sheng automation equipment co., LTD.,
link: http:www.onewwww.com
Reviews
There are no reviews yet.